03/24/92 Clementine Design Begins.
01/25/94 Spacecraft launched at Vandenburg Air Force Base.
02/03/94 Departure from low Earth orbit following an eight day checkout period.
02/19/94 Following two phasing loop orbits, Clementine injected into lunar orbit. Lunar orbit, shake down period begins.
02/26/94 Start of systematic mapping for first cycle.
03/26/94 First mapping cycle complete, start of second cycle.
04/21/94 Second mapping cycle complete, begin special observations.
05/05/94 Leave Lunar Orbit.
05/07/94 Clementine satellite suffered on-board malfunction that prevents planned close fly-by of the near-Earth Asteroid Geographos.
08/31/94 Planned Geographos Fly-by (not accomplished).

Clementine

Home Tour Join! Contents Team News Catalog Search Comm
ASI W9600887r1.1. Copyright © 2004 Artemis Society International, for the contributors. All rights reserved.
This web site contains many trade names and copyrighted articles and images. Refer to the copyright page for terms of use.
Maintained by ASI Web Team <asi-web@asi.org>.
Submit update to this page. Maintained with WebSite Director. Updated Sun, Aug 8, 1999.